RAG status, milestones and progress against plan for your weekly status report. Update the numbers or upload a CSV, then export the slide.

New here? — takes 2 minutes.

Project status dashboard

CRM migration — Week 39

Overall status

Amber
was Green

Percent complete

57%
+6 pts

Budget used

52%
of $2.4m

Days to go-live

68
go-live 4 Dec

Workstream status

Data migration, warning48%
Integrations, good62%
Sales process config, good70%
Reporting, critical35%
Training and change, warning40%

Key milestones

MilestoneBaselineForecast
Design sign-off, good10 Jul10 Jul
Test migration 2, serious18 Sep02 Oct
UAT complete, warning06 Nov13 Nov
Go-live, warning04 Dec04 Dec

Planned vs actual complete (%)

PlannedActual
0
20
40
60
80
Planned: 20Actual: 22
Planned: 30Actual: 31
Planned: 40Actual: 38
Planned: 48Actual: 45
Planned: 55Actual: 51
Planned: 62Actual: 57
AprMayJunJulAugSep

Open issues by severity

31Issues
Critical2 6%
High7 23%
Medium13 42%
Low9 29%

4 Project Status Dashboard templates

Every template opens as a finished dashboard. Pick the closest one, then change anything.

Metrics and how to calculate them

The KPIs these templates are built on, with the formula behind each one.

RAG status
Red, amber or green against agreed thresholds, e.g. green within 5% of plan, amber 5–10%, red over 10% or needing escalation.
Percent complete
Completed work ÷ total planned work × 100, by tasks, effort or earned value.
Milestone slip
Forecast date − baseline date, in days, for each milestone.
Milestone on-time rate
Milestones completed on or before baseline ÷ milestones completed × 100.
Budget used
Actual cost to date ÷ approved budget × 100; compare with percent complete.
Throughput
Tasks or deliverables completed per week, used to forecast the finish date.

How to make your Project Status Dashboard

Pick a template, put your numbers in, download — about two minutes. Nothing to install; the PDF and every other format come with a SlideTeam plan.

  1. 1

    Pick your dashboard

    Click Pick Your Dashboard. This dashboard has 4 ready-made layouts, such as Weekly status report and Milestone tracker. Each opens finished, with example figures.

  2. 2

    Change the numbers

    Point at any widget (tap it on a phone) and choose Edit to type or paste its numbers and labels — a column copied from Excel pastes straight in. Click the dashboard's title to rename it.

  3. 3

    Use your own data

    Upload CSV or Excel takes a CSV, .xlsx or .xls file and shows exactly what it read: pick the sheet, the label column and how repeated rows are combined (sum, average, count), then Build a new dashboard or Fill this template with your columns. Not sure of the layout? Download the sample CSV and replace the numbers.

  4. 4

    Download PDF, PowerPoint, Excel and more

    Download (right end of the toolbar) lists every format: a PDF (free), PowerPoint with native charts you can still edit (right-click › Edit data), a report pack (summary slide plus one slide per chart) as PowerPoint or PDF, Excel (opens on a Dashboard sheet with live charts) and a CSV for Power BI, Tableau or Google Sheets.

  5. 5

    More options: add widgets, brand it, share

    More options (top right) shows the rest: Add widget puts in a chart, KPI tile, table, funnel or a Text / commentary box; the arrows on a widget move it and ✕ removes it; click the subtitle to edit it. Customise sets the currency, template language, slide size, brand colour and logo. Sheets / Slides shows how to open your file in Google Sheets or Slides; Share copies a link to this exact dashboard.

Common questions

What is a RAG status dashboard?

A dashboard that rates each project or workstream red, amber or green against thresholds for schedule, budget, scope and resources. Agree the thresholds in advance so the colors mean the same thing every week.

What should a weekly project status report include?

Overall RAG and why it changed, progress against plan, the next milestones with forecast dates, and the top issues. The Weekly status report template fits that on one slide.

How do I track milestones?

List each milestone with owner, baseline date, forecast date and slip. The Milestone tracker template does this and adds a monthly planned vs achieved chart.

Can I reuse this slide every week?

Yes. Download the PowerPoint once, then either update it in PowerPoint or come back, edit the numbers here and download again.

Goes well with this — from our other free tools

The figures in the example dashboards are illustrative and exist so each page shows a finished dashboard rather than an empty grid. Replace them with yours before sharing anything.