Construction Progress Report Builder

Monthly site report for clients and lenders: progress by package, cost and schedule against plan, safety record, issues and the next month’s look-ahead.

Your numbers

MetricUnitBetterTargetActual September 2026August 2026vs targetvs lastStatusOwnerCommentary (blank = written for you)
−3 pt+8 ptClose
−2.1%+17.8%On target
—+50%Off track
——On target
+46.7%+15.8%Off track

Paste rows straight from Excel or Google Sheets into any cell · Sample CSV · Leave Commentary blank and it is written from the numbers.

Slides

Click a slide to edit it. Hidden slides stay here but are left out of the download.

1Cover
September 2026Month review

Kestrel Construction

Progress Report No. 9 — Riverside Offices

Frame complete; envelope 9 days behind schedule

Site project manager

2Executive summary

Kestrel Construction · September 2026

Executive summary

A mixed September 2026: some targets hit, with clear gaps to close.

  • 2 of 5 metrics on or above target, 1 close and 2 off track.
  • Strongest result: Lost-time incidents at 0, better than target.
  • Needs attention: Schedule variance at 9 days against a 0 days target.
  • 1 of 4 metrics improved on August 2026.

Written from your numbers. Edit to write your own.

2On target
1Close
2Off track
Progress Report No. 9 — Riverside Offices2 / 7
3KPI scorecard

Kestrel Construction · September 2026

KPI scorecard

Overall completeClose
55%
Target 58%▼3 pt
vs August 2026▲8 pt
Cost to dateOn target
$13.9M
Target $14.2M▼2.1%
vs August 2026▲17.8%
Schedule varianceOff track
9 days
Target 0 days—
vs August 2026▲50%
Lost-time incidentsOn target
0
Target 0—
vs August 2026—
RFIs openOff track
22
Target 15▲46.7%
vs August 2026▲15.8%
Progress Report No. 9 — Riverside Offices3 / 7
4Workstream status

Kestrel Construction · September 2026

Progress by package

WorkstreamStatusProgressDueOwner
SubstructureComplete100%CompleteGroundworks
Steel frameComplete100%CompleteSteel contractor
Envelope and claddingPanel delivery lateAt risk40%Dec 2026Cladding contractor
Mechanical and electricalOn track30%Mar 2027M&E
Fit-outNot started0%May 2027Fit-out
Progress Report No. 9 — Riverside Offices4 / 7
5Trend chart

Kestrel Construction · September 2026

Planned vs actual % complete

PlannedActual
0
15
30
45
60
5855
MayJunJulAugSep
Progress Report No. 9 — Riverside Offices5 / 7
6Risks and issues

Kestrel Construction · September 2026

Risks and issues

Risk or issueImpactMitigationOwnerStatus
Cladding panel deliveryHighSecond fabricator for south elevationPackage managerAt risk
Winter weather on roof worksMediumTemporary roof cover orderedSite managerAt risk
Progress Report No. 9 — Riverside Offices6 / 7
7Next steps

Kestrel Construction · September 2026

Look-ahead: October

ActionOwnerDue
01Recover 5 days on claddingPackage manager31 Oct
02Close 10 RFIs with architectDesign manager24 Oct
Progress Report No. 9 — Riverside Offices7 / 7

About the Construction Progress Report Builder

It opens on the Monthly client progress report template (7 slides): report for the client meeting on a commercial build. Pick a Review switches to one more template: Weekly site report (short weekly site update for the project team).

The example numbers track Overall complete, Cost to date, Schedule variance, Lost-time incidents and RFIs open. Each metric has a target, an actual and last period's figure. The builder works out the variance, scores it red, amber or green (costs and other lower-is-better metrics the right way round) and writes a sentence of commentary from the numbers, which you can overwrite. Paste rows from Excel, upload a CSV, edit any slide's words, and hide or add slides.

Download an editable PowerPoint deck built from native tables and charts, with talking points in the speaker notes, and an Excel workbook whose variance and status are live formulas. Save the review as a small file and, next period, open it and press Next period. It is free, with no sign-up, and nothing is stored.

2 Construction Progress Report templates

Each opens with example numbers. Switching keeps nothing from your edits, and Undo brings them back.

How to use the Construction Progress Report Builder

  1. 1

    Pick a review

    Click Pick a Review. This page has 2 ready-made templates, such as Monthly client progress report and Weekly site report. Each opens as a finished deck with example numbers.

  2. 2

    Put your numbers in

    Type each metric's target, actual and last period in Your numbers, paste rows from Excel, or use Upload CSV or Excel. Status, variance and commentary update as you type.

  3. 3

    Edit the slides

    Click any slide to change its words. Hide what you don't need, or use Add slide for wins, risks, next steps and more. Undo (Ctrl+Z) reverses any change.

  4. 4

    Download

    Download lists every format: a free PDF of the slides, an editable PowerPoint deck with native tables and charts, and Excel with variance and status as formulas. The Review file is a small file: next period open it and press Next period.

Start from a spreadsheet: download the sample CSV, fill it in and upload it.

Terms used in this review

Schedule variance
Days ahead (negative) or behind (positive) the baseline schedule.
RFI
Request for information: a formal design question to the architect or engineer.

Common questions

What goes in a construction progress report?

Overall % complete against schedule, progress by package or trade, cost to date against budget, health and safety, RFIs and issues, risks and a look-ahead for the next period.

Can I add site photos?

Download the PowerPoint and drop photos onto any slide; every element stays editable.

How do I show planned vs actual progress?

Edit the trend chart slide with planned and actual % complete by month.

Is it free?

Yes, free with no sign-up.

Can I download the construction progress report as PowerPoint or Excel?

Yes. The PowerPoint deck is built from native text, tables and charts you can edit, with commentary in the speaker notes, and the Excel workbook keeps variance and status as live formulas. Both are free, with no sign-up.

Goes well with this — from our other free tools

Example figures and names are illustrative. Replace them with yours before sharing anything.